Estimated Schedule

Capital Project: Estimated schedule

Interior Finish Work SessionPhase 1:  January 2015 – January 2016

  • Contractor mobilize, job trailers and site fences installed
  • Demolition of James Law Auditorium and VEC Plaza
  • Renovations of Schurman Hall E-Wing Levels 1 &2
  • Renovations for new locker rooms, VMIT suite and faculty offices

Summer Phase 1:  May 2015 – August 2015

  • Renovations Gross Anatomy Lab
  • Renovations Wet Lab
  • Renovate for Clinical Skills Support and Simulation Labs

Phase 2:  January 2016 – June 2017

  • Demolish old Diagnostic Lab, Library and VEC Atrium
  • Construct new building

Summer Phase 2:  May 2016 – August 2016

  • Renovate Clinical Skills Lab
  • Replace VRT Curtain Wall

Total Project Completion:   June 2017